Question: Using the priority list G,F,E,D,C,B,A schedule the project described by the project digraph shown in Fig 8-34 using N=3 processors. Show the project timeline and

Using the priority list G,F,E,D,C,B,A schedule

Using the priority list G,F,E,D,C,B,A schedule the project described by the project digraph shown in Fig 8-34 using N=3 processors. Show the project timeline and give its finishing time. Please show work out.

A(8) D(12) F(1) B(5) START(0) END (O) C(9) E(6) G(2) FIGURE 8-34