Question: Using the project above and the following status information ( below ) at the end of day 1 4 , calculate / determine the following:

Using the project above and the following status information (below) at the end of day 14, calculate/determine the following:
Total 12 Marks (4 for the rough work AND the values for each answer as per below)
a) Total project PV (Planned Value)(2 marks)
b) Total project EV (Earned Value)(2 marks)
c) Total project AC (Actual Cost)(1 mark)
d) Project performance with respect to cost and schedule (1 mark)
e) Estimate at completion & how much more / less money is required to complete the project (1 mark)
f) Forecasted duration & how many more / less days are required to complete the project (1 mark)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!