Using the risk equation, how would leadership assess the following facts: supply chain disruption can impact your
Fantastic news! We've Found the answer you've been seeking!
Question:
Using the risk equation, how would leadership assess the following facts: supply chain disruption can impact your business at the rate of $250K per day. You estimate a power outage lasting one day can occur for your operations with a probability set to 0.09%. What is the risk?