Question: Using the table below, determine the overall duration of the project. Activity Duration IPA A 2 none B 3 A C 2 A D 5
-
Using the table below, determine the overall duration of the project.
Activity Duration IPA A 2 none B 3 A C 2 A D 5 B, C A 12 days
B 10 days
C 9 days
D 5 days