Question: Using the table below, determine the overall duration of the project. Activity Duration IPA A 2 none B 3 A C 2 A D 5

  1. Using the table below, determine the overall duration of the project.

    Activity Duration IPA
    A 2 none
    B 3 A
    C 2 A
    D 5 B, C
    A

    12 days

    B

    10 days

    C

    9 days

    D

    5 days