Question: VCALCULATIONS USING SPREADSHEET 5 . 1 Assignment For the project given in the previous slide: Draw the AON diagram for the project. In the diagram

VCALCULATIONS USING SPREADSHEET
5.1 Assignment
For the project given in the previous slide:
Draw the AON diagram for the project. In the diagram
all calculations for ES, EF, LS and LF should be
performed
Calculate the total and free float for each activity and
determine the critical path.
Re-perform all calculations using a spread sheet (MS
Excel) and compare the calculations resulted from the
AON diagram.
Draw a Gaunt Chart for the project plan (Activities
versus Time)
 VCALCULATIONS USING SPREADSHEET 5.1 Assignment For the project given in the

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!