Question: View Policies Current Attempt in Progress Using the following project information, calculate the variance for each of the project activities. Most Likely Time Estimates (weeks)

View Policies Current Attempt in Progress Using

View Policies Current Attempt in Progress Using the following project information, calculate the variance for each of the project activities. Most Likely Time Estimates (weeks) Pessimistic Time Estimates (weeks) Activity A B D E F G H I Activity A B D E F G H Optimistic Time Estimate(weeks) I 2 2.5 5 3 4 2 4 6 5 2 (Round your answers to 2 decimal places, e.g. 1.75.) 3 Variance 4 7 5 8 5 5 6 8 3 5 5 8 7 15 8 6 8 11 3 Immediate Predecessor(s) none A A B.C B,C D 7