Question: Watch the video first. Import Project P 6 Assignment 5 - 2 . xer, add Planned Labor Units for each activity ( under status

Watch the video first.
Import Project "P6 Assignment 5-2.xer", add Planned Labor Units for each activity (under status tab: of the activities), based on the following table. Keep duration type as Fixed duration & units
Screenshot 2023-03-01135509.png
No need to add Milestones S and E.
Budgeted Labor units = Planned Labor units
Add activity "project admin" as "level of effort", and connect it to the activity network using proper dependencies (it should be started when the project begins and ended with the project)(Hint: SS and FF). Take the following screenshots:
Gantt chart without summary bars but include the level of efforts. (10 points)
We decided that "Student page design" can be conducted at the same time as "Faculty/staff page design" (sharing the same predecessors and successors). Make changes to the existing relationships accordingly. Take the following screenshots:
Gantt chart without summary bars, but include the level of efforts (10 points)
Critical Path only (not the entire activity network), without WBS grouping. (10 points)
When changing relationships between activities, you should always delete the existing dependencies and set up the new ones. Because only one relationship can exist between two activities.
Always remember to click the schedule button to get the updated schedule and critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!