Question: Watch the video first. Import Project P 6 Assignment 5 - 2 . xer, add Planned Labor Units for each activity ( under status
Watch the video first.
Import Project P Assignment xer", add Planned Labor Units for each activity under status tab: of the activities based on the following table. Keep duration type as Fixed duration & units
Screenshot png
No need to add Milestones S and E
Budgeted Labor units Planned Labor units
Add activity "project admin" as "level of effort", and connect it to the activity network using proper dependencies it should be started when the project begins and ended with the projectHint: SS and FF Take the following screenshots:
Gantt chart without summary bars but include the level of efforts. points
We decided that "Student page design" can be conducted at the same time as "Facultystaff page design" sharing the same predecessors and successors Make changes to the existing relationships accordingly. Take the following screenshots:
Gantt chart without summary bars, but include the level of efforts points
Critical Path only not the entire activity network without WBS grouping. points
When changing relationships between activities, you should always delete the existing dependencies and set up the new ones. Because only one relationship can exist between two activities.
Always remember to click the schedule button to get the updated schedule and critical path.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock