Question: WBS ElementPlanned Value ( PV ) Earned Value ( EV ) Actual Cost ( AC ) 2 . 0 1 Airframe 4 8 , 0

WBS ElementPlanned Value (PV)Earned Value(EV)Actual Cost(AC)2.01 Airframe48,00048,00050,0002.02 Engines22,00021,00023,0002.03 Avionics80,00060,00045,0002.04 Communications30,00030,00030,0002.05 Tech. Manuals42,00042,00048,0002.06 Spares40,00035,00042,0002.07 Training80,000180,00086,000Project Total342,000316,000324,000Figure 14-1 Drug Surveillance Aircraft Project-Monthly Performance Report (October 31,20XX)Consider the project performance report presented in Figure 14-1. What valid conclusion can you draw regarding the project cost performance as of October 31,20XX?