Question: We have a project with the following tasks. Each task has a completion time, as well as a list of predecessors: Task Completion Time Predecessor

We have a project with the following tasks. Each task has a completion time, as well as a list of predecessors:
Task Completion Time Predecessor
A 4-
B 7-
C 8-
D 7 A,B
E 11 B,C
F 8 D
G 6 E
H 5 F
I 7 F,G
J 3 G
If we are spending $6,625/week in labor costs, how much do we expect to spend overall in labor costs? _________________