Question: We have a project with the following tasks. Each task has a minimum, expected, and maximum completion time, as well as a list of predecessors:

We have a project with the following tasks. Each task has a minimum, expected, and maximum completion time, as well as a list of predecessors:
Task Completion Time Predecessor
A 7-
B 7-
C 8 A
D 7 B
E 9 C
F 8 C,D
G 6 D
What is the project completion time?