Question: Week 3 Activity % Complete Actual Cost Earned Value Planned Value Schedule Variance Cost Variance Schedule Performance Index Cost Performance Index Assess User Requirements 80%

Week 3
Activity % Complete Actual Cost Earned Value Planned Value Schedule Variance Cost Variance Schedule Performance Index Cost Performance Index
Assess User Requirements 80% $20,000
Assess Current System 100% $32,000
Cumulative

Estimate at Completion
Estimate to Complete
To Complete Performance Index

Comment on if the project is on time/budget or not based on the calcualtions.