Question: Week 3 Activity % Complete Actual Cost Earned Value Planned Value Schedule Variance Cost Variance Schedule Performance Index Cost Performance Index Assess User Requirements 80%
Week 3 Activity % Complete Actual Cost Earned Value Planned Value Schedule Variance Cost Variance Schedule Performance Index Cost Performance Index Assess User Requirements 80% $20,000 Assess Current System 100% $32,000 Cumulative
| Estimate at Completion | |
| Estimate to Complete | |
| To Complete Performance Index |
Comment on if the project is on time/budget or not based on the calcualtions.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
