Question: Were conducting EVM for one task. The task was baselined at 12 days. We are presently at the end of day 14. We are confident

Were conducting EVM for one task. The task was baselined at 12 days. We are presently at the end of day 14. We are confident this task will take 2 more day. Assume an Hourly Rate of $10 per hour. Calculate PV, EV, AC, BAC, CV, CPI, SV, SPI, EAC, ETC, VAC, PCIB & PCIC. Show the formula and answer for each.