Question: What are characteristics you should consider during pre-project planning? Select all that apply. 1. Major construction activities such as mobilization, earthwork, foundation, super structure, exterior

What are characteristics you should consider during pre-project planning? Select all that apply.

1.

Major construction activities such as mobilization, earthwork, foundation, super structure, exterior enclosure, interior finishes.

2.

Site conditions such as overhead power lines and site accessibility

3.

Overall project schedule to analyze what trades will be working, when they will be working , and if work by multiple trades would be going on concurrently.

4.

Site Logistics such as where the site trailer will be located, where storage containers will be located, etc.

5.

Construction sequencing such as where you will start the excavation, from which side will you begin steel erection, etc.

6.

Project specific hazards such as excavation depths and whether or not benching the excavation is appropriate or if other excavation control measures would be more appropriate.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!