Question: What different components make up a work breakdown structure ( WBS ) ? 1 point A document of all the work assigned to team members
What different components make up a work breakdown structure WBS
point
A document of all the work assigned to team members along with stakeholders' comments
One list of all the tasks to complete on a project
Milestones and tasks for the project organized in a hierarchy
List of details on a project with team member feedback