Question: What does not accurately describe the work breakdown structure (WBS)/task list? Select one: a. It is a list of activities showing the tasks that need
What does not accurately describe the work breakdown structure (WBS)/task list?
Select one:
a. It is a list of activities showing the tasks that need to be completed and who will complete the task.
b. It allows project deliverables and work to be divided into manageable tasks and subtasks.
c. It requires sequencing of tasks prior to project scheduling.
d. It helps ensure no tasks have been omitted.