Question: What does represent in project scheduling, signifying the latest possible completion time for an activity without causing a delay to the critical path, with the

What does represent in project scheduling, signifying the latest possible completion time for an activity without causing a delay to the critical path, with the difference between early finish and late finish being the total float?A) Late Finish (LF)B) Final Conclusion Time (FCT)C) End Delay Threshold (EDT)D) Critical Path Boundary (CPB)