Question: What does the forward pass method in CPM help to determine? a . The earliest start and finish times for each activity b . The
What does the forward pass method in CPM help to determine?
a
The earliest start and finish times for each activity
b
The project scope and deliverables
c
The total project budget and resource needs
d
The latest finish time for each activity