Question: What does the term critical path refer to in project scheduling?A . The shortest path through the project scheduleB. The longest sequence of tasks that
What does the term "critical path" refer to in project scheduling?A The shortest path through the project scheduleB. The longest sequence of tasks that determines the minimum project durationC. The path with the most resources allocatedD. The path with the least risk