Question: What is the activity slack for c? i am getting 1 but it tells me its incorrect..... Assume the network and data in the following

What is the activity slack for c? i am getting 1 but it tells me its incorrect.....

What is the activity slack for c? i am getting 1
Assume the network and data in the following Table A: Immediate Time ACTIVITY Predecessor (weeks) (s) A -- 3 B -- 4 C B 4 D A 4 E A, B 5 F D, E 6 G C, E 2