Question: What is the C pk for the process if upper specification limit is 101 feet, lower specification limit is 99.5 feet, process mean is 99.8

What is the Cpk for the process if upper specification limit is 101 feet, lower specification limit is 99.5 feet, process mean is 99.8 feet, and process standard deviation is 0.02 feet?

1.09

5

20

1.10

0.83