Question: what is the correct answer? Table below gives the activities of a project, their predecessor(s), and their durations. The minimum number of arcs that should

what is the correct answer?
Table below gives the activities of a project, their predecessor(s), and their durations. The minimum number of arcs that should be used to draw the network of this project is Activity Predecessor Duration A 2 4 C A 8 D A 4 B F D 8 G C, E, F 9Step by Step Solution