Question: what is the correct answer? Table below gives the activities of a project, their predecessor(s), and their durations. The minimum number of arcs that should

what is the correct answer? Table below gives the

what is the correct answer?

Table below gives the activities of a project, their predecessor(s), and their durations. The minimum number of arcs that should be used to draw the network of this project is Activity Predecessor Duration A 2 4 C A 8 D A 4 B F D 8 G C, E, F 9