Question: What is the critical path and the project duration? 2. Given the following information for a project: Immediate Predecessor(s) Activity 1-2 2-3 2-4 3-4 3-5

What is the critical path and the project duration?
What is the critical path and the project
2. Given the following information for a project: Immediate Predecessor(s) Activity 1-2 2-3 2-4 3-4 3-5 3-6 4-6 5-6 5-7 6-7 Time (in days) 4 4 3 4. 5 5 2 4 3 4 1-2 1-2 2-3 2-3 2-3 2-4, 3-4 3-5 3-5 3-6, 4-6,5-6 a) Construct a network diagram. b) Identify all paths in the network. c) Determine each path's length. d) Identify the Critical Path(s). e) Calculate the expected project duration