Question: What is the 'critical path' in project management for construction projects? A ) The shortest possible path to complete the project B ) The longest

What is the 'critical path' in project management for construction projects?
A) The shortest possible path to complete the project
B) The longest sequence of activities that must be finished on time for the project to complete on due date
C) The most expensive set of activities
D) The sequence of activities with the least amount of slack