Question: What is the 'critical path' in project management for construction projects? A ) The shortest possible path to complete the project B ) The longest
What is the 'critical path' in project management for construction projects?
A The shortest possible path to complete the project
B The longest sequence of activities that must be finished on time for the project to complete on due date
C The most expensive set of activities
D The sequence of activities with the least amount of slack