Question: What is the critical path? Question 4 options: The earned value of a given activity The overall duration of a project The sequence of activities
What is the critical path?
Question options:
The earned value of a given activity
The overall duration of a project
The sequence of activities that represents the longest path through a project, which determines the shortest possible duration.