Question: What is the earliest finish for Task C given the following information? Predecessor task A: earliest finish 8; predecessor task B: earliest finish 4; successor

What is the earliest finish for Task C given the
What is the earliest finish for Task C given the following information? Predecessor task A: earliest finish 8; predecessor task B: earliest finish 4; successor task D: earliest start 10; task C: time duration 6. 18 O 10 24 14