Question: What is the expected total time for this project with logical relationships and activity durations shown? Also, assess the critical path on the diagram. Assumptions:
- What is the expected total time for this project with logical relationships and activity durations shown?
Also, assess the critical path on the diagram.
Assumptions:
- Arrows indicate activities. Arrows show durations of activities in days.
- All lettered Phases must be executed.
- Start with A-plan and end with Z-deploy.

Expected total time and Critical path?
- 16, ASCTZ
- 19, ABPNZ
- 20, ABDCTZ
- 25, ASCDBPNZ
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock