Question: What is the minimum completion time for the project after crashing (until no more crashing is possible)? 18 weeks 20 weeks 22 weeks 25 weeks

What is the minimum completion time for the

What is the minimum completion time for the project after crashing (until no more crashing is possible)?

18 weeks

20 weeks

22 weeks

25 weeks

Egon Spengler is planning a charity benefit gala for his "Save the City" campaign. However, because one of his partners, Peter Venkman, has difficulty staying on task, the project is scheduled and they are running out of time. Egon has used project management principles to lay out the task relationships and he finds that if they follow the traditional schedule, as outlined below, they will not have enough time to get everything done before the weekend of the gala. Egon has created a list of tasks, their time requirements, and their relationships. He has also begun a network diagram, but needs to know what to do next. He knows that he needs to reduce the total time by five weeks. Activity Duration (weeks) Crash Time (weeks) Description Preceding Crashing Activity(ies) Cost/Week A 4 2 Determine gala theme $520 B 6 6 Reserve portal location for gala $250 6 4 Create Marketing Plan B $680 D 6 6 Ray Parker, Jr. to audition musical acts B $620 E 7 Determine ticket sales method $350 F 5 2 Purchase supplies including Stay Puff marshmallows $200 G 5 2 Pick musical act and sign contract D $380 4 3 Sell tickets in person E $720 3 3 Sell tickets online E $150 1 Gala! HI, F. G H D

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!