Question: What is the project critical path Network Diagram: Case Kitchen Remodel ID# Activity Name ( Subtasks ) Predecessor ID# ( s ) Duration Budget 1

What is the project critical path
Network Diagram: Case Kitchen Remodel
ID#
Activity Name (Subtasks)
Predecessor ID#(s)
Duration
Budget
1
Planning and Design (Define Project Scope, Create Design, Select Materials, Finalize Design
3
$600
2
Obtain Permits (Look up building codes, Submit applications, Wait for permits, Solve compliance issues)
1
3
$300
3
Demolition and Preparation (Remove current fixtures, cabinetry and appliances, Remove debris, Seal off adjacent areas, prepare site to begin construction)
2
4
$700
4
Plumbing and Electrical (Install plumbing for sink and appliances, upgrade and install electrical wiring, check for correct placement and check for code compliance)
3
5
$1500
5
Install New Flooring (Select flooring, prep subfloor, install flooring, seal and finish the flooring.)
4
3
$1100
6
Cabinet Installation (Prep and assemble cabinets, install lower and upper cabinets, check alignment and secure mounting, install the cabinet hardware)
5
4
$2500
7
Install Countertops (Prep and measure, install, finish and seal the edges, check fittings around sink and appliances)
6
2
$1500
8
Install Appliances (Place appliances, connect the appliances to plumbing/electrical, make any adjustments)
6,7
1
$2000
9
Painting and finishing adjustments (paint walls and ceilings, install backsplash, paint touch up around cabinets and fixtures, prep and clean kitchen for use)
6,7
3
$500
10
Cleanup and Inspection (Inspect for and issues, address issues, remove debris and coverings, finalize documentation of project)
9
2
$300
.
.
Budget at Completion:
$11,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!