Question: what key input is required before a project can be moved to a closing phrase (choose 1 only) a. Accepted deliveribles b. Updated issues log
what key input is required before a project can be moved to a closing phrase (choose 1 only)
a. Accepted deliveribles
b. Updated issues log
c. work performance reviews
d. change requests
The analysts 1st dicounts the expected future value of both project cost and benefits, (a dollar tomrrror is less than today) then subtracts the discounted project cost from the stream of benefits. which of the below options describes this
a. BRC
b. PP
C. IRR
D. NPV