Question: What statement best describes the link between schedule variance (SV) and the project schedule? Group of answer choices SV reflects whether the project is ahead

What statement best describes the link between schedule variance (SV) and the project schedule? Group of answer choices SV reflects whether the project is ahead of, behind, or on schedule. SV indicates which milestones on the critical path are likely to be missed. SV predicts whether the total project budget will be spent by the scheduled completion date. SV shows how much time each work package has consumed as compared to the planned duration