Question: whats the correct answer with duration The critical path for the network activities shown below is Immediate Predecessors Activity B D E Duration 4 2

whats the correct answer
whats the correct answer with duration The
with duration The critical path for the network activities shown below is Immediate Predecessors Activity B D E Duration 4 2 9 4 5 A B,C,D O A C-E: 14 B. A-B-D: 10 C. A-B-C-D-E; 24 OD. A-B-E 11 O E A-D-E; 13