Question: The critical path for the network activities shown below is Immediate Activity Duration Predecessors A 12 B 8 6 A, B D 4 A E

The critical path for the network activitiesThe critical path for the network activities

The critical path for the network activities shown below is Immediate Activity Duration Predecessors A 12 B 8 6 A, B D 4 A E 5 B, C, D O ACDE O ADE O ACE O None of the above