Question: When a project management tMost projects have one critical path, but it's possible to have multiple critical paths. If other factors stay the same, how
When a project management tMost projects have one critical path, but it's possible to have multiple critical paths. If other factors stay the same, how does project risk usually change as the number of critical paths increase? Question 28Select one: a. it decreases b. it increases c. it stays the same d. that trend is generally unpredictableeam used the term "expert judgment", who can qualify as an expert? Question 21Select one: a. members of the project team b. subject matter experts within the organization c. key stakeholders d. any of the above may qualify