Question: When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or
When a project manager must reduce project duration but resources are constrained, creating a software program that will have less functionality than originally planned or building a house without the bonus room and the basement that the owner originally specified in the plans would both be examples of
Multiple Choice
fasttracking.
use criticalchain project management.
reduce project scope.
compromise quality.
do it twicefast and correctly.