Question: When a project's net present value ( NPV ) exceeds zero, then: the project should be accepted the project will be acceptable using the payback
When a project's net present value NPV exceeds zero, then:
the project should be accepted
the project will be acceptable using the payback period method
the IRR should be calculated to ensure that the project's IRR exceeds the cost of capital
the payback period is always less than one year
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
