Question: When a project's NPV exceeds zero, a. The project will also be acceptable using payback criteria. b. The IRR should be calculated to insure that
When a project's NPV exceeds zero, a. The project will also be acceptable using payback criteria. b. The IRR should be calculated to insure that the project's projected rate of return exceeds the required rate of re c. The project should be accepted without any further consideration, assuming we are confident that the cash flow 2. and the required rate of return have been properly estimated. d. All of the above are correct
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
