Question: When a project's NPV exceeds zero, A. the project will always be accepted when payback period method is used. B. the IRR should be calculated
When a project's NPV exceeds zero,
| A. | the project will always be accepted when payback period method is used.
| |
| B. | the IRR should be calculated to insure that the project's projected rate of return exceeds the cost of capital.
| |
| C. | the project should be accepted without any further consideration, assuming we are confident that the cash flows and the cost of capital have been properly estimated.
| |
| D. | only answers a and c are correct.
| |
| E. | none of the statements above is correct. |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
