Question: When a project's NPV exceeds zero, A. the project will always be accepted when payback period method is used. B. the IRR should be calculated

When a project's NPV exceeds zero,

A.

the project will always be accepted when payback period method is used.

B.

the IRR should be calculated to insure that the project's projected rate of return exceeds the cost of capital.

C.

the project should be accepted without any further consideration, assuming we are confident that the cash flows and the cost of capital have been properly estimated.

D.

only answers a and c are correct.

E.

none of the statements above is correct.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!