Question: When calculating the critical path for a three time estimate project, you use the Blank _ _ _ _ _ _ as the activity duration
When calculating the critical path for a three time estimate project, you use the Blank as the activity duration time.
Multiple choice question.
most likely time
expected time
optimistic time
pessimistic time