Question: When customers order pizza ( task 1 ) , a pizza box is configured ( task 2 ) while the pizza is baked ( task
When customers order pizza task a pizza box is configured task while the pizza is baked task Baking the pizza takes the most time task In this process, task and task are completed at the same time in parallel Therefore, Order task and bake task
contain slack time
make up the critical path
have configure box task as a dependency
all of the answers are correct
none of the answers are correct