Question: When customers order pizza (task 1), a box is constructed (task 2) while the pizza is baked (task 3). Baking the pizza takes the most
When customers order pizza (task 1), a box is constructed (task 2) while the pizza is baked (task 3). Baking the pizza takes the most time (task 3). In this process, task 2 and task 3 are completed at the same time or (in parallel.) Therefore, Order (task 1) and bake (task 3) _______.
A. contains slack time
B. make up the critical path
C. have construct box (task 2) as a dependency
D. all of the answers are correct
E. none of the answers are correct