Question: When deciding on whether to crash project activities or not, a project manager was faced with the following information. Activities of the critical path are

When deciding on whether to crash project activities or not, a project manager was faced with the following information. Activities of the critical path are highlighted with an asterisk:
Normal Crashed
Activity Cost Duration Extra Cost Duration
A 5,0004 weeks 4,0003 weeks
B*10,0005 weeks 3,0004 weeks
C 3,5002 weeks 3,5001 week
D*4,5006 weeks 4,0004 weeks
E*1,5003 weeks 2,5002 weeks
F 7,5008 weeks 5,0007 weeks
G*3,0007 weeks 2,5006 weeks
H 2,5006 weeks 3,0005 weeks
1. What is the projects normal critical path and duration of project?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!