Question: M6-2 Assignment When deciding on whether to crash project activities or not, a project manager was faced with the following information. Activities of the critical

M6-2 Assignment

When deciding on whether to crash project activities or not, a project manager was faced with the following information. Activities of the critical path are highlighted with an asterisk:

Normal Crashed
Activity Cost Duration Extra Cost Duration
A 5,000 4 weeks 4,000 3 weeks
B* 10,000 5 weeks 3,000 4 weeks
C 3,500 2 weeks 3,500 1 week
D* 4,500 6 weeks 4,000 4 weeks
E* 1,500 3 weeks 2,500 2 weeks
F 7,500 8 weeks 5,000 7 weeks
G* 3,000 7 weeks 2,500 6 weeks
H 2,500 6 weeks 3,000 5 weeks

1. What is the project's normal critical path and duration of project?

2. Calculate the 'Per week cost' for crashing each activity.

3. Identify the sequencing of the activities to be crashed in the first four steps. Which of the critical activities should be crashed first? Why?

4. After four iterations involving crashing project activities, what has the critical path shrunk to? (Assume all noncritical paths are < a fully crashed critical path. - In other words, critical path tasks will not change) - Show calculations.

5. Suppose project overhead costs accrued at a fixed rate of $500 per week. Also assume that a project penalty clause kicks in after 19 weeks. The penalty charged is $5,000 per week. When the penalty charges are added, what does the total project cost curve look like? Develop a table listing the costs accruing on a per-week basis.

6. If there were no penalty payments accruing to the project, would it make sense to crash any project activities? Show your work.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!