Question: When developing the estimates for project phases, you choose to add the individual estimates for the activities comprising each phase. What type of estimation method

When developing the estimates for project phases, you choose to add the individual estimates for the activities comprising each phase. What type of estimation method are you using?
a.
Analogous estimating.
b.
Top-down estimating.
c.
Parametric estimating.
d.
Bottom-up estimating.