Question: When developing the project team, identify the ONE CORRECT statement regarding how the team will be developed. A. The team will work through all of
When developing the project team, identify the ONE CORRECT statement regarding how the team will be developed.
A. The team will work through all of the "stages" and will take the same amount of time "developing" through each stage.
B. The team will work through all of the "stages" but the "Norming" stage will always take the longest to complete.
C. The team will only work through the "stages" of development that the Project Manager deems to be needed.
D. The team will always work through each of the major "stages", although some of the stages may be shorter in length if the team has worked together in the past.