Question: When evaluating a project network diagram, which determines critical path Group of answer choices activities with a start - finish dependency activities with no slack
When evaluating a project network diagram, which determines critical path
Group of answer choices
activities with a startfinish dependency
activities with no slack or float
the sequence of activities that shows the shortest path through the network
the path with the most activities