Question: When evaluating a project network diagram, which determines critical path q , the path with the most activities activities with a start - finish dependency

When evaluating a project network diagram, which determines critical path q,
the path with the most activities
activities with a start-finish dependency
the sequence of activities that shows the shortest path through the network q,
activities with no slack (or float)
 When evaluating a project network diagram, which determines critical path q,