Question: When evaluating a project network diagram, which determines critical path Group of answer choices the path with the most activities activities with a start -

When evaluating a project network diagram, which determines critical path
Group of answer choices
the path with the most activities
activities with a start-finish dependency
the sequence of activities that shows the shortest path through the network
activities with no slack (or float)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!