Question: When evaluating a project network diagram, which determines critical path Group of answer choices the path with the most activities activities with a start -
When evaluating a project network diagram, which determines critical path
Group of answer choices
the path with the most activities
activities with a startfinish dependency
the sequence of activities that shows the shortest path through the network
activities with no slack or float