Question: When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the

When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is
Group of answer choices
Over Allocated.
Time-Constrained.
Ahead of schedule.
Institutionally Challenged.